The Electricity Generating Authority of Thailand (EGAT) anticipates approval from the Cabinet for its proposal to increase energy generation at its south Bangkok gas-fired facility in Samut Prakan. The initiative lately underwent a public listening to.
The proposal for extra capacity is out there in response to the decommissioning of several generators. To guarantee sufficient electricity for the capital’s inhabitants, EGAT deemed this growth essential. The demand for electricity in Bangkok and the encompassing provinces makes up half of the nation’s whole demand, which stands at 34,000 megawatts.
EGAT’s plan encompasses the construction of three recent energy generation services, all contributing to a mixed capacity of two,490 megawatts. This will complement the prevailing 1,232 megawatts capability of the south Bangkok power plant.
Environmental authorities have permitted the new generators, subsequently permitting EGAT to conduct a public listening to. Following the hearing, a public response report shall be submitted to the cupboard for ultimate approval, as disclosed by Piyanuch Klansorn, the Energy Regulatory Commission’s director for environment and energy industry monitoring.
The public session, performed online on September 17, noticed the participation of 500 residents, energy authorities, and officers from the Phuchao Saming Phray Tambon Administration Organisation. Somsak Kaewsena, head of Samut Prakan’s Muang district, revealed that locals have shown eager curiosity within the project and have provided priceless suggestions for the brand new generators’ administration.
EGAT estimates the development of the new generators to require 50.eight billion baht. The authority plans to seek Cabinet approval for the venture within the coming yr. Once approval is secured, the development of the services is slated to begin within the latter half of 2024. Hurry are set to start out operations between 2026 and 2027.
Two mills, one with a capability of 338 megawatts and the opposite with 629 megawatts, have been decommissioned by EGAT in 2020 and 2022, respectively. The authority maintains that the capability boost is important to ensure enough electricity for Bangkok’s residents.
Currently, Thailand’s power generation capacity in reserve stands at just 30% of the entire capacity. Thus, EGAT believes it’s paramount that the country secures a extra strong power supply.